Bally's faces Chicago aldermen today as $1.7B casino construction standoff enters its second month
Bally's appears before Chicago's license committee on 9 September as its month-long freeze on hotel and amenity construction at the $1.7B River West casino remains unresolved.

Bally's Corporation faces a public hearing before Chicago's Committee on License and Consumer Protection today, 9 September 2026, as the company's freeze on non-gaming construction at its $1.7 billion River West casino complex enters its second month with no resolution in sight. The standoff - triggered by Chicago's decision to legalise video gambling terminals - has idled roughly 1,500 union tradespeople and put the project's hotel, restaurants, and events center in limbo while the casino floor itself remains on track for an early 2027 opening.
The dispute
Chicago's $16.6 billion 2026 city budget, passed by the City Council over Mayor Brandon Johnson's objection, lifted the city's long-standing ban on video gambling terminals in bars, restaurants, truck stops, and fraternal organisations. Bally's argues the move breaches its 2022 Host Community Agreement, under which the city committed not to expand gaming while Bally's held its exclusive casino licence.
On 9 August 2026, Bally's notified the Chicago Community Builders Collective - the minority-led general contracting partnership overseeing the project - that it was "resetting the pace of construction" on all non-gaming elements of the complex. The affected work includes:
- A 34-story, 500-room hotel tower
- An events center and 3,000-seat theatre
- Multiple planned restaurants
The casino floor itself was not paused. Bally's said it does not take the decision lightly "because of the potential impact on many of the 1,500 union tradespeople who have been working hard to build Bally's Chicago."
Aldermen push back - and question the motive
Twenty-seven members of the City Council signed a letter demanding Bally's resume full construction, calling the pause a violation of the host agreement. A further letter from 28 aldermen followed in mid-August. Some council members have gone further, questioning whether the VGT dispute is a pretext for financial difficulties.
"Many of us suspect that this is really a cash-flow issue for Bally's and they're trying to turn lemons into lemonade by blaming VGT as the reason they're slowing down construction," said 43rd Ward Alderman Brendan Reilly, citing the company's disclosed debt load of more than $5 billion.
Bally's has rejected that framing. In a letter sent to aldermen on 26 August 2026, executive Chris Jewett argued that VGT competition is a greater threat to the project than the company's own finances, and presented revenue comparisons to support the claim. Bally's has also retained law firm RKF Global - which employs former Mayor Lori Lightfoot - to navigate the dispute.
The company is also reportedly weighing whether to withhold a $4 million annual host-community payment due to the city this month. Under the original 2022 agreement, the city collected $40 million upfront plus $4 million per year in exchange for granting Bally's exclusive rights to slot machines within city limits.
Temporary licence extended; permanent opening still spring 2027
Separately, the Illinois Gaming Board approved an extension of Bally's temporary casino licence at the Medinah Temple in River North, allowing operations to continue from 6 September 2026 through 9 September 2027 - a 12-month reprieve tied to provisions in the state's Revenue Omnibus Bill signed into law this summer. The extension removes the risk of a revenue gap between the temporary and permanent venues.
The permanent casino at 560 W. Grand Avenue - built on the 30-acre former Chicago Tribune Freedom Center printing plant - is designed to include 3,400 slot machines, 173 table games, a 500-room hotel, a 3,000-seat theatre, 10 food and beverage venues, and a two-acre public riverfront park. The project has already missed two prior opening targets, slipping from 2025 to September 2026 and now to spring 2027.
The outcome of today's hearing will determine whether Bally's and the city can reach a negotiated settlement on VGTs or whether the dispute escalates to litigation - a path that could further delay the hotel and amenity construction that 1,500 Chicago union workers are waiting to resume.
Written by Construction Trade News's automated desk from the sources above and reviewed before publication. How we work.
Related
EquipmentBobcat's R2-Series mini excavators bring load-sensing hydraulics to the 1-2 tonne class
Bobcat's new R2-Series mini excavators - the E16, E17z, E19 and E20z - replace the M-Series with SmartFlow load-sensing hydraulics, cutting fuel use by up to 18% and noise by 4 dBA.
9 Sept 2026
EquipmentJCB adds Dual Drive to its 3CX and 4CX backhoe loaders, letting operators reposition from the excavator seat
JCB has introduced a Dual Drive system for its 109 hp 3CX and 4CX backhoe loaders, allowing operators to move the machine without leaving the excavator controls - cutting downtime between digging cycles.
9 Sept 2026Bechtel completes all seven trains at Cheniere's Corpus Christi Stage 3 LNG plant in Gregory, Texas
Bechtel handed over the seventh and final liquefaction train at Cheniere's Corpus Christi Stage 3 project on 28 August 2026, closing out a four-year EPC contract ahead of schedule and on budget.
9 Sept 2026